Triton Naval Architects
   
 
 
 
 
 
 
 


featured projects

Novel or "different" projects, current or past.

 

M.V. MAGSENGER 2 - LOWER ENGINE REMOVAL - Dec 2011 / Jan 2012

The Magsenger 2, is a brand new 250mx60m Bulkcarrier, which underwent engine problems on maiden voyage that necessitated the removal and replacement of the lower crankcase. However the more tricky part is the engine weighs 360 tonnes, is 3 decks high, and the ship was built around it. The lower section to be removed weighs some 140 tonnes, and the upper section, once stripped down, which needs to be lifted and suspended, also weighs about 140 tonnes. Hence significant support mechanisms had to be put in place. This is where Triton came in, contracted by Dormac, who were the main ship repair contractor. Triton were tasked to perform all the design and analysis works necessary to lift and support, jack and move the relevant large mass components. These various design drawings and reports then distributed for review and acceptance by third parties. These modifications included the necessity to cut a large access hole in the bulkhead that seperates the engine room and the 7th Hold, to allow the replacement parts to be lifted out of, and into, the hold and then slide into the engine room on custom designed rails and bogey systems.

A more detailed project description along with analysis plots will follow when time allows, but in the meantime, some project photo's can be see on HERE. The project is ongoing.

NMP PHOSHATE SAMPLING - LAUNCH AND RECOVERY SYSTEM

A generic sampling system was developed through a series of concepts, through to detail design and fabrication, whereby the unit can fit onto any applicable Offshore Supply Vessel / Anchor Handler, for NMP (Namibian Marine Phosp[hates, Pty Ltd.

The system recovers samples from the seabed up to 400m waterdepth, using a custom designed Grab (by Arlona Engineering) and is handled via a A Frame, and Winch Tower, Hopper, Conveyor Unit, to allow for bagging on deck. Triton were the principle design contractors and project managers. Basic Hydraulics and Control System were responsible for the design and supply of all hydraulics and control components of the system, and worked with Triton in a close and all inclusive arrangement, with the owners themselves. This arrangement extended through all the concept design phases leading up to detail design, fabrication and installation. BELMET won the contract for fabrication, workshop installation and onboard installation. The system has been installed on the Smit Madura for its first sampling excersize.

KENMARE FLOATING TREATMENT PLANT - All Floating Aspects, Pontoon Design, Strongback Design, All Equipment Foundations and Surge Bin Support

Triton, working together with (initially Akersolutions, and then EP-C) are responsible for the pontoons and strongbacks, along with all other deck foundations, that support the new Floating Treatment Plant for KENMARE, for the Moma Titanium Dune Mining Project. Areas of responsibility include, the pontoon structural design, structural interfacing with column loading from the plant above, flotation, stability, mooring etc. Analysis works include global model floating analysis with blobal bending, plus local modelling of strongbacks structures with prescribed bending and external loading, in static stress and buckling.

ZAMBEZI FERRIES

A series of River-Crossing-Ferries have been designed, with the first one built and commissioned by Mike Bullock at Kazungula, Botswana, with the 2nd well under construction. More detail and a link to photo's will be updated when time allows:

 

TRISTAN BARGE

A novel idea for low cost, transportable barge is this Tristan Barge, using the concept of connecting plastic floats tied together with a strong lattice structure frame and wooden deck. This barge has a 20tonne carrying capacity and has already been highly successful at the island of Tristan, in the use of transhipping cargo between visiting cargo vessels and the harbour, where draft limitation restrict access by those ships. It was also easily transportable to the island and could be launched from a single point lift from the ship.

100tonne CHAIN PULLER - Student Intern Design Project

With Salvage companies or salvage operations often in need of a means to apply large shore based forces on a structure, or standard ship, or even capsized vessel (like the case of the Laverne which capsized in the harbour), Triton (together with Basic Hydraulics) identified the need to develop the design of a 100t Chain Puller.

Such chain pullers could be used in isolation or any number coupled together through a common control system. This student intern design project (under taken by Morne Le Roux of Stellenbosch University) included the concept design, structural analysis, hydraulic equipment, such that should an inquiry come in, Triton together with Basic Hydraulics could go into production at relatively short notice.

WESTERN CHALLENGE and SHELF EXPLORER - Likely Conversion / Refit - 2009 / 2010

The Western Challenge is a Ore Transport Barge, recently aquired by Kenmare (owners of the Bronagh J, Transport Vessel, designed by Triton, featured here).

Preliminary and conceptual design and studies have been undertaklen for the refit of the Tug assisted Western Challenge to be made fit for purpose at MOMA MOZAMBIQUE to supplement the Bronagh J.

NEW DOUBLE SKIN BUNKER BARGE & DOUBLE SKINNING EXISTING BUNKER BARGES

The double skin SMIT LIPUMA fuel bunker barge was designed by Triton, and build by Dormac in Durban. She was launched in Nov 2007, and due to come into service early 2008.

The design of the double skinning of the exisiting Pentow Energy, has been completed, with construction due to begin early 2008.

For more detail, click here

MOMA BARGE

A self loading, self unloading, self propelled manned barge was designed, for construction in Singapore.

The barge is to be ABS classed, and transports 4000tonnes of Titanium based raw product between a custom built jetty near Moma, in Mozambique, and discharge in an awaiting handimax bulk carrier, some 7 to 10 Nm offshore. Typically 10 trips between the loading jetty and the bulk carrier would required, to load the ship.

Some 600 000 tonnes of product is expected to be shipped per year.

For more detail, click here:

NAVAL VESSEL DISPUTE SETTLEMENT

Triton Naval Architects were contracted by Price Waterhouse Coopers (Kenya) to assist in the dispute settlement over the procurement of the new build Lloyds classed, Naval Vessel "Jasiri", built in Spain for the Kenyan Navy. An ongoing involvement between 2007 and 2010/11.

SAIBOS DOCKING

In Jan 2006 saw the eventual dcking of the FPS SAIBOS, after much pre-planning w.r.t. to docking block arrangement and the design and analysis of a stern frame, which would be capable of supporting 2000 tonnes at 8m above the dock floor.

Due to the ship have a significant folding stern tower, it was deemed necessary by the owners that the stern should be supported by a dedicated frame capably of such support.

The ship had never previously been docked with the stern tower installed.

She was again docked in Cape Town in June 2010, using the same concept, but a rebuilt stern docking frame. This frame was also due to be stress monitored "live" during the docking process, using submerged strain gauging, installed on the frame, ahead of flooding the dock, all conducted under subcontract by Origen (Hout Bay).

For more detail, click here:

VARIOUS MOORING ANALYSIS

Non-linear dynamic (time domain) mooring analysis were performed on a number of Oil Rigs and FPSO's as listed below.

F.P.S.O. Glas Dowr (2003)

Semi Sub - South Seas Driller (Pride South Seas)

Semi Sub - Gavea Lifter / Sedco 709

F.P.S.O Dalia

Semi Sub - Orca

Semi Sub - Atlantic Venture

Semi Sub - Transocean Richardson

Semi Sub - Scarabeo

FPSO - Glas Dowr (2009)

Semi Sub - Sedex 701 (2009)

Jack Up - Hercules 185 (2009)

Semi Sub - Transocean Celtic Sea 2011

These were all analysed for static moorings for extended periods of stay in Cape Town, Walvis Bay, or Saldanha Bay and assumed 10yr return wind and gust speeds, or other applicable client supplied data. These time based analysis would then predict peak line tensions, bollard reactions, fender reactions and displacements off and along the quay. Single line failure analysis would also be performed, as required by the various approval authorities.

 

 

 

 




Triton Naval Architects
No. 8 Foregate Square, Harbour Rd
Foreshore, Cape Town, SOUTH AFRICA
Tel: +27 21 418 2090 | Fax: +27 21 425 2722 | Email: triton@triton.co.za

By Triton Naval Architects



Powered by NETdentity

 
 

photos

     
 

NMP Phosphates Sampling System being installed on the Smit Madura

 
     
 

Structural Stress Analysis of the Pontoons and Strongbacks, of the Kenmare Floating Treatment Plant

 
 
 

KAZUNGULA FERRY - Carries trucks, cars and people across the Zambezi River

 
     
 

MOMA BARGE - MV "Bronagh J" in operation in Mozambique

 
     
 

TRISTAN BARGE - 20 tonne carrying capacity. Seen here being launched in Tristan.

 
     
 

100 tonne CHAIN PULLER

 
     
 

WESTERN CHALLENGE - Moored in Dampier Australia

 
     
 

JASIRI - Naval Corvette / Patrol Vessel built for Kenyan Navy - TNA assisting PWC in dispute settlement.

 
 

SAIBOS DOCKING FRAME